Running a non-conformance process that actually closes

How to raise, assign, correct and verify NCRs so they close properly, and the habits that stop a backlog building up.

The Traklio team · · 2 min read

Every project produces non-conformances. That isn't the problem. The problem is the NCR that gets raised, half-answered and forgotten, until it reappears at handover when the fix costs the most and the people who understood it have moved on.

A good non-conformance process is less about the form and more about the flow: who owns the NCR at each moment, and what has to happen before it can move on.

The lifecycle of an NCR

A non-conformance that closes properly passes through the same stages every time:

  1. Raised: what is wrong, where, against which requirement, with photos.
  2. Classified: how serious it is, and whether work in the area must stop.
  3. Assigned: the party responsible for the fix, with a due date.
  4. Corrected: the corrective action proposed and carried out, with evidence.
  5. Verified: someone other than the person who fixed it checks the fix on site.
  6. Closed: signed off, with the record complete.

The step most often skipped is verification. An NCR closed on the subcontractor's word alone isn't closed; it's waiting to come back.

Write the NCR so someone else can act on it

The person fixing the problem is often not the person who found it. A good NCR states:

  • What the requirement is: the clause, drawing or standard.
  • What was found: measured or observed, not interpreted.
  • Where exactly: grid line, level, room or chainage.
  • The evidence: photos and readings, taken at the time.

Avoid writing the solution into the NCR. The responsible party proposes the corrective action; you accept or reject it.

Ownership and due dates

An NCR without an owner belongs to nobody. Every open NCR should have one named party responsible for the next step and a date it's due. When that date passes, the right people should know without anyone having to chase.

Note: Track the age of open NCRs, not just their number. Twenty NCRs closed within a week is a healthy site. Five NCRs open for three months is a problem.

Root cause, not just repair

Repeat NCRs on the same activity are a signal. When the same defect appears twice, ask why: an unclear drawing, a missing hold point in the ITP, a new crew, a material issue. Fixing the cause is cheaper than raising the third NCR.

Habits that stop a backlog

  • Review open NCRs at every weekly quality meeting, oldest first.
  • Never let an NCR leave the site team without an owner.
  • Make verification someone else's job, never the person who did the fix.
  • Link each NCR to the inspection or ITP activity that found it.
  • Close NCRs on evidence, never on a phone call.

How Traklio helps

In Traklio an NCR always has an owner and a due date, moves through its stages in order, and can't be closed by the person who raised the fix. Overdue items are flagged automatically, every photo and decision is on the record, and you can see the open NCRs for any project, area or subcontractor in seconds.